Blue Star Crystal Chsl, Borivali West
by Paradigm Blue Star LLP · Borivali West, Mumbai 400092 · Map
- Launched
- Mar 20234 yrs 4 mths promised
- Possession (MahaRERA)
- Jul 2027Not extended
- Concrete structure
- 98%Mid-construction
- Booked
- –
- Buildings
- 10.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 7
- 3 BHK
- 22
- 4 BHK
- 1
- 5+ BHK
- 1
- Other units
- 14
- Total units
- 45
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 98% | 85% | 47 | |
| 100% | 98% | 85% | – | |
| 100% | 98% | 85% | – | |
| 100% | 98% | 85% | 47 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 2 yrs 8 mths |
| Possession date extended | No | 3 of 6 |
| Possession date (MahaRERA) | Jul 2027 | Feb 2027 |
| Concrete structure (RCC) | 98% | 100% |
| Units booked | – | 55% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Kamla Borivli Rajesh, Borivali West
- Gopal Terrace Co-operative Housing Society LTD, Borivali West
- Sparkle Umadarshan, Borivali West
- Aureate, Borivali West
- West Avenue, Borivali West
- State Sector Bank Employees Chs Ltd Kailas Building, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kamla Borivli Rajesh | March 2023 | March 2027 | 100% | 14 units booked out of 23 units for sale |
| Gopal Terrace Co-operative Housing Society LTD | April 2023 | January 2027 | 100% | 12 units booked out of 12 units for sale |
| Sparkle Umadarshan | June 2023 | December 2026 | 100% | 13 units booked out of 13 units for sale |
| Aureate | December 2022 | June 2027 | 95% | 14 units booked out of total 28 units |
| West Avenue | June 2023 | March 2026 | 100% | 10 units booked out of total 21 units |
| State Sector Bank Employees Chs Ltd Kailas Building | June 2023 | July 2027 | 100% | 16 units booked out of 43 units for sale |
About this project
Blue Star Crystal Chsl by Paradigm Blue Star LLP is a 45-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in March 2023 with possession due in July 2027. The concrete structure (RCC) is 98% complete.
Read full summary
Blue Star Crystal Chsl is a BMC-sanctioned project by Paradigm Blue Star LLP in Borivali West, Mumbai 400092, registered with MahaRERA as P51800049927. It was launched in March 2023. It has 45 units in 1 building: 31 homes (2, 3, 4 and 5+ BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 98% complete, final finishes 85% complete.
Paradigm's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 5,095 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 8 |
| Possession date extended on the builder's application | 2 |
| MahaRERA complaints (filed by or against the builder), all Paradigm projects | 91 (5 of 9 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.