Kamla Borivli Rajesh, Borivali West
Ready to move
by Kamla Homes And Lifestyles Private Limited · Borivali West, Mumbai 400092 · Map
- Launched
- Mar 20234 yrs promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 14 of 2361% · 63 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale14 booked out of 23 units
Rehab63 units for existing members
Total 86 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 5
- 2 BHK
- 28
- 3 BHK
- 32
- 5+ BHK
- 1
- Other units
- 20
- Total units
- 86
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 23
- Rehab units
- 63
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 14 | |
| 100% | 100% | 0% | 12 | |
| 100% | 100% | 0% | 9 | |
| 100% | 70% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400092
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs | 3 yrs 8 mths |
| Possession date extended | No | 2 of 4 |
| Possession date (MahaRERA) | Mar 2027 | Jul 2027 |
| Concrete structure (RCC) | 100% | 99% |
| Units booked (free sale) | 61% | 44% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Blue Star Crystal Chsl, Borivali West
- Meghalok Heights, Borivali West
- State Sector Bank Employees Chs Ltd Kailas Building, Borivali West
- Bhavik Darshan Chs Ltd And Gajmukh Chs Ltd, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Blue Star Crystal Chsl | March 2023 | July 2027 | 98% | – |
| Meghalok Heights | December 2022 | December 2026 | 35% | 24 units booked out of 55 units for sale |
| State Sector Bank Employees Chs Ltd Kailas Building | June 2023 | July 2027 | 100% | 16 units booked out of 43 units for sale |
| Bhavik Darshan Chs Ltd And Gajmukh Chs Ltd | June 2023 | December 2027 | 100% | 32 units booked out of 70 units for sale |
About this project
Kamla Borivli Rajesh by Kamla Homes And Lifestyles Private Limited is an 86-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in March 2023 with possession due in March 2027. 14 units booked out of 23 units for sale. The concrete structure (RCC) is complete.
Read full summary
Kamla Borivli Rajesh is a BMC-sanctioned project by Kamla Homes And Lifestyles Private Limited in Borivali West, Mumbai 400092, registered with MahaRERA as P51800049969. It was launched in March 2023. It has 86 units in 1 building: 66 homes (1, 2, 3 and 5+ BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 86 units, 23 are for sale and 63 are rehab units for existing members.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
14 units booked out of 23 units for sale (61%). Since the July 2026 update, 2 more units have been booked.