- Launched
- Apr 20232 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2026Extended by 8 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 52 of 7272% · 64 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale52 booked out of 72 units
Rehab64 units for existing members
Total 136 units. Rehab units are not for sale.
Project facts
- Other units
- 136
- Total units
- 136
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 72
- Rehab units
- 64
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 52 | |
| 100% | 98% | 70% | 52 | |
| 100% | 88% | 35% | 45 | |
| 100% | 55% | 18% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
The Waterfront by M/s Orbit Developers is a 136-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in April 2023; its MahaRERA registration has lapsed. 52 units booked out of 72 units for sale. The concrete structure (RCC) is complete.
Read full summary
The Waterfront is a BMC-sanctioned project by M/s Orbit Developers in Bandra West, Mumbai 400050, registered with MahaRERA as P51800050617. It was launched in April 2023. It has 136 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 136 units, 72 are for sale and 64 are rehab units for existing members.
Possession was due in April 2026, after an extension of 8 months from the original August 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.
52 units booked out of 72 units for sale (72%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 98% to 100%.