24 Karat, Jogeshwari West
by Paper Mill Plant and Machinery Manufacturers Limited · Jogeshwari West, Mumbai 400102 · Map
- Launched
- May 20235 yrs 10 mths promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 63%Mid-construction
- Booked (free sale)
- 157 of 16993%
- Buildings
- 30.9 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale157 booked out of 169 units
Land-owner share31 units, not for sale
Total 200 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 68
- 2 BHK
- 122
- Other units
- 10
- Total units
- 200
- Buildings
- 3
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 169
- Land-owner share (not for sale)
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 63% | 30% | 157 | |
| 100% | 63% | 30% | 131 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 89 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400102
Projects with 90–400 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 10 mths | 3 yrs 7 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Mar 2029 | Dec 2026 |
| Concrete structure (RCC) | 63% | 100% |
| Units booked (free sale) | 93% | 94% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 3 projects
- One Jogeshwari, Jogeshwari West
- Vista Residences, Jogeshwari West
- Dream Aspire, Jogeshwari West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| One Jogeshwari | May 2023 | December 2026 | 100% | 119 units booked out of 123 units for sale |
| Vista Residences | November 2023 | Dec 2028 – Jun 2029 | 0% | 176 units booked out of total 212 units |
| Dream Aspire | December 2023 | December 2026 | 100% | 121 units booked out of total 129 units |
About this project
24 Karat by Paper Mill Plant and Machinery Manufacturers Limited is a 200-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in May 2023 with possession due in March 2029. 157 units booked out of 169 units for sale. The concrete structure (RCC) is 63% complete.
Read full summary
24 Karat is a BMC-sanctioned project by Paper Mill Plant and Machinery Manufacturers Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800050840. It was launched in May 2023. It has 200 units in 3 buildings: 190 homes (1 and 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 200 units, 169 are for sale and 31 are the land-owner's share, not for sale.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 63% complete, final finishes 30% complete.
157 units booked out of 169 units for sale (93%). Since the July 2026 update, 26 more units have been booked.