Vista Residences, Jogeshwari West

by Vista Developers Mumbai LLP · Jogeshwari West, Mumbai 400102 · Map

Launched
Nov 2023First of 2 phases
Possession (MahaRERA)
Dec 2028 – Jun 2029Not extended
Concrete structure
0%Weighted across 2 phases
Booked
176 of 21283%
Buildings
20.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
130
3 BHK
74
Other units
8
Total units
212
Buildings
2
Land
0.2 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Vista Residences Wing-D Tower -3
Early stage
P518000536251020%86%
Vista Residences Wing C Tower 2
Early stage
P518000767201020%80%
Show updates by phase

Vista Residences Wing-D Tower -3 (P51800053625)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%91
100%0%0%91
100%0%0%48
100%0%0%48

"–" means MahaRERA shows no figure for that update.

Vista Residences Wing C Tower 2 (P51800076720)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%85
100%0%0%85
25%0%0%18
25%0%0%18

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 63%Dec 2025: Excavation 63%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

How to read construction stages

Compared with 4 similar projects in PIN 400102

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs3 yrs 4 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)Dec 2028 – Jun 2029Dec 2027
Concrete structure (RCC)0%82%
Units booked83%93%
MahaRERA complaints (filed by or against the builder)01

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Vista Residences by Vista Developers Mumbai LLP is a 212-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, registered with MahaRERA in 2 phases, with possession dates from December 2028 to June 2029. 176 units booked out of total 212 units. Work on the concrete structure (RCC) has not started.

Read full summary

Vista Residences is a BMC-sanctioned project by Vista Developers Mumbai LLP in Jogeshwari West, Mumbai 400102, registered with MahaRERA as 2 phases (P51800053625, P51800076720). The first phase was launched in November 2023. Together the phases have 212 units in 2 buildings: 204 homes (2 and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.

The phases' registered possession dates run from December 2028 to June 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. Neither phase has its structure complete.

176 units booked out of total 212 units (83%).