- Launched
- May 20232 yrs 4 mths originally promised
- Possession (MahaRERA)
- Mar 2026Extended by 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 11 of 1479% · 1 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale11 booked out of 14 units
Rehab1 unit for existing members
Total 15 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 2
- 2 BHK
- 13
- Total units
- 15
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 14
- Rehab units
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 11 | |
| 100% | 100% | 30% | 11 | |
| 100% | 100% | 0% | 11 | |
| 100% | 75% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Kingston by Empire Lifespaces LLP is a 15-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in May 2023; its MahaRERA registration has lapsed. 11 units booked out of 14 units for sale. The concrete structure (RCC) is complete.
Read full summary
Kingston is a BMC-sanctioned project by Empire Lifespaces LLP in Mulund West, Mumbai 400080, registered with MahaRERA as P51800051143. It was launched in May 2023. It has 15 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 15 units, 14 are for sale and 1 is a rehab unit for existing members.
Possession was due in March 2026, after an extension of 6 months from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
11 units booked out of 14 units for sale (79%).