Rang Tarang Co Op Hsg Society Ltd, Dahisar
by Rang Tarang Chs Ltd · Dahisar, Mumbai 400068 · Map
- Launched
- Jun 20234 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 85%Mid-construction
- Booked (free sale)
- 51 of 7271% · 50 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale51 booked out of 72 units
Rehab50 units for existing members
Total 122 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 60
- 2 BHK
- 30
- 3 BHK
- 32
- Total units
- 122
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 72
- Rehab units
- 50
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 85% | 10% | 51 | |
| 100% | 85% | 0% | 51 | |
| 100% | 60% | 0% | 51 | |
| 100% | 60% | 0% | 39 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400068
Projects with 60–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 6 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Aug 2026 |
| Concrete structure (RCC) | 85% | 100% |
| Units booked (free sale) | 71% | 68% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Krishna Kripa, Dahisar
- Sahakar Vista, Dahisar
- Nageshwar Sra Chs, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Krishna Kripa | October 2023 | August 2026 | 100% | 26 units booked out of 38 units for sale |
| Sahakar Vista | November 2023 | July 2026 | 100% | 113 units booked out of total 117 units |
| Nageshwar Sra Chs | November 2023 | December 2026 | 52% | 17 units booked out of 36 units for sale |
About this project
Rang Tarang Co Op Hsg Society Ltd by Rang Tarang Chs Ltd is a 122-unit MHADA-sanctioned project in Dahisar, Mumbai 400068, launched in June 2023 with possession due in December 2027. 51 units booked out of 72 units for sale. The concrete structure (RCC) is 85% complete.
Read full summary
Rang Tarang Co Op Hsg Society Ltd is a MHADA-sanctioned project by Rang Tarang Chs Ltd in Dahisar, Mumbai 400068, registered with MahaRERA as P51800051613. It was launched in June 2023. It has 122 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 122 units, 72 are for sale and 50 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes 10% complete.
51 units booked out of 72 units for sale (71%).