Nageshwar Sra Chs, Dahisar

by Vishwambhar Constructions · Dahisar, Mumbai 400068 · Map

Launched
Nov 20233 yrs 1 mth promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
52%Mid-construction
Booked (free sale)
17 of 3647% · 44 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale17 booked out of 36 units

Rehab44 units for existing members

Total 80 units. Rehab units are not for sale.

Project facts

1 BHK
75
Other units
5
Total units
80
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
36
Rehab units
44
Reserved units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)52%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 52%Jul 2026: Concrete structure (RCC) 52%Oct 2026: Concrete structure (RCC) 52%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 52%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%52%0%17
100%52%0%17
100%52%0%17
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth3 yrs 4 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2026Mar 2027
Concrete structure (RCC)52%100%
Units booked (free sale)47%85%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Nageshwar Sra Chs by Vishwambhar Constructions is an 80-unit project in Dahisar, Mumbai 400068, launched in November 2023 with possession due in December 2026. 17 units booked out of 36 units for sale. The concrete structure (RCC) is 52% complete.

Read full summary

Nageshwar Sra Chs is a project by Vishwambhar Constructions in Dahisar, Mumbai 400068, registered with MahaRERA as P51800053512. It was launched in November 2023. It has 80 units in 1 building: 75 homes (1 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 80 units, 36 are for sale and 44 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 52% complete, final finishes not started.

17 units booked out of 36 units for sale (47%).