Alfa Padma Vasant, Mulund East

Lapsed

by Zakiruddin Gaffar Sayyed · Mulund East, Mumbai 400081 · Map

Launched
Jul 20232 yrs 11 mths promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
60%Mid-construction
Booked (free sale)
0 of 40%
Buildings
1
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 4 units

Land-owner share4 units, not for sale

Total 8 units. Land-owner units are not for sale.

Project facts

1 BHK
1
2 BHK
7
Total units
8
Buildings
1
Phases
1
MahaRERA complaints
0
Free-sale units
4
Land-owner share (not for sale)
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%0
100%60%0%0
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Alfa Padma Vasant by Zakiruddin Gaffar Sayyed is an 8-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in July 2023; its MahaRERA registration has lapsed. 0 units booked out of 4 units for sale. The concrete structure (RCC) is 60% complete.

Read full summary

Alfa Padma Vasant is a BMC-sanctioned project by Zakiruddin Gaffar Sayyed in Mulund East, Mumbai 400081, registered with MahaRERA as P51800051797. It was launched in July 2023. It has 8 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 8 units, 4 are for sale and 4 are the land-owner's share, not for sale.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

0 units booked out of 4 units for sale (0%).