by Gurukul Realty LLP · Andheri West, Mumbai 400053 · Map

Launched
Jul 20233 yrs 5 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
0%Early stage
Booked (free sale)
43 of 6072% · 20 rehab units
Buildings
10.3 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale43 booked out of 60 units

Rehab20 units for existing members

Total 80 units. Rehab units are not for sale.

Project facts

2 BHK
10
3 BHK
25
Other units
45
Total units
80
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
4
Free-sale units
60
Rehab units
20
Reserved units
41

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation10%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 10%Dec 2025: Excavation 10%Jul 2026: Excavation 10%Oct 2026: Excavation 10%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 10%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
10%0%0%43
10%0%0%–
10%0%0%–
10%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400053

Projects with 10–70 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths3 yrs 5 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)0%75%
MahaRERA complaints (filed by or against the builder)40

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Tapodhan by Gurukul Realty LLP is an 80-unit project in Andheri West, Mumbai 400053, launched in July 2023 with possession due in December 2026. 43 units booked out of 60 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Tapodhan is a project by Gurukul Realty LLP in Andheri West, Mumbai 400053, registered with MahaRERA as P51800052166. It was launched in July 2023. It has 80 units in 1 building: 35 homes (2 and 3 BHK) and 45 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 80 units, 60 are for sale and 20 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation 10% complete, structure (RCC) not started, final finishes not started.

43 units booked out of 60 units for sale (72%).