Mdm Maestro, Andheri West

by Mdm Realty LLP · Andheri West, Mumbai 400053 · Map

Launched
Jan 20231 yr 11 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
100%Nearing possession
Booked (free sale)
13 of 2357% · 23 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 23 units

Rehab23 units for existing members

Total 46 units. Rehab units are not for sale.

Project facts

1 BHK
27
2 BHK
18
4 BHK
1
Total units
46
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
23
Rehab units
23

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 30%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%13
100%100%0%13
100%100%0%13
100%30%0%5

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400053

Projects with 20–100 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 11 mths3 yrs 6 mths
Possession date extendedBy 2 yrs0 of 4
Possession date (MahaRERA)Dec 2026Sep 2026
Concrete structure (RCC)100%88%
Units booked (free sale)57%74%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Mdm Maestro by Mdm Realty LLP is a 46-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in January 2023 with possession due in December 2026. 13 units booked out of 23 units for sale. The concrete structure (RCC) is complete.

Read full summary

Mdm Maestro is a BMC-sanctioned project by Mdm Realty LLP in Andheri West, Mumbai 400053, registered with MahaRERA as P51800048676. It was launched in January 2023. It has 46 units in 1 building, with 1, 2 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 23 are for sale and 23 are rehab units for existing members.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes not started.

13 units booked out of 23 units for sale (57%).