Mahavir Krupa CHSL Ltd, Borivali West
Ready to move
by M/s Shri Neelkanth Developers & Builders · Borivali West, Mumbai 400092 · Map
- Launched
- Jul 20232 yrs 8 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 1 yr
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 0 of 90% · 12 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 9 units
Rehab12 units for existing members
Total 21 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 3
- 2 BHK
- 6
- 3 BHK
- 3
- Other units
- 9
- Total units
- 21
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 9
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 0 | |
| 100% | 100% | 90% | 0 | |
| 100% | 100% | 0% | 0 | |
| 100% | 50% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400092
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 2 yrs 6 mths |
| Possession date extended | By 1 yr | 3 of 5 |
| Possession date (MahaRERA) | Mar 2027 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 0% | 71% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- West Avenue, Borivali West
- Sparkle Umadarshan, Borivali West
- Gopal Terrace Co-operative Housing Society LTD, Borivali West
- Rishabraj Aradhana, Borivali West
- The Capital, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| West Avenue | June 2023 | March 2026 | 100% | 10 units booked out of total 21 units |
| Sparkle Umadarshan | June 2023 | December 2026 | 100% | 13 units booked out of 13 units for sale |
| Gopal Terrace Co-operative Housing Society LTD | April 2023 | January 2027 | 100% | 12 units booked out of 12 units for sale |
| Rishabraj Aradhana | October 2023 | July 2026 | 100% | 5 units booked out of 7 units for sale |
| The Capital | February 2023 | April 2028 | 80% | 29 units booked out of total 43 units |
About this project
Mahavir Krupa CHSL Ltd by M/s Shri Neelkanth Developers & Builders is a 21-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in July 2023 with possession due in March 2027. 0 units booked out of 9 units for sale. The concrete structure (RCC) is complete.
Read full summary
Mahavir Krupa CHSL Ltd is a BMC-sanctioned project by M/s Shri Neelkanth Developers & Builders in Borivali West, Mumbai 400092, registered with MahaRERA as P51800052181. It was launched in July 2023. It has 21 units in 1 building: 12 homes (1, 2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 9 are for sale and 12 are rehab units for existing members.
Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
0 units booked out of 9 units for sale (0%).