The Capital, Borivali West

by Ans Lifestyle Realtors LLP · Borivali West, Mumbai 400092 · Map

Launched
Feb 20232 yrs 3 mths originally promised
Possession (MahaRERA)
Apr 2028Extended by 2 yrs 11 mths
Concrete structure
80%Mid-construction
Booked
29 of 4367% · 22 in Jul 2026
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
12
Other units
31
Total units
43
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Reserved units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 47%Jul 2026: Concrete structure (RCC) 67%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 80%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%0%29
100%67%0%22
100%47%0%15
100%0%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400092

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths2 yrs 10 mths
Possession date extendedBy 2 yrs 11 mths3 of 4
Possession date (MahaRERA)Apr 2028Feb 2027
Concrete structure (RCC)80%100%
Units booked67%56%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

The Capital by Ans Lifestyle Realtors LLP is a 43-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in February 2023 with possession due in April 2028. 29 units booked out of total 43 units. The concrete structure (RCC) is 80% complete.

Read full summary

The Capital is a BMC-sanctioned project by Ans Lifestyle Realtors LLP in Borivali West, Mumbai 400092, registered with MahaRERA as P51800049366. It was launched in February 2023. It has 43 units in 1 building: 12 homes (1 RK) and 31 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, extended by 2 years 11 months from the original May 2025. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.

29 units booked out of total 43 units (67%). Since the July 2026 update, 7 more units have been booked, the reported concrete structure (RCC) has gone from 67% to 80% and the possession date has moved from May 2026 to April 2028.