Shraddha Paradise, Borivali West
by Shraddha Prime Projects Limited · Borivali West, Mumbai 400092 · Map
- Launched
- Aug 20235 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 30%Mid-construction
- Booked (free sale)
- 141 of 20868% · 148 rehab units
- Buildings
- 12 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale141 booked out of 208 units
Rehab148 units for existing members
Total 356 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 15
- 2 BHK
- 235
- 3 BHK
- 106
- Total units
- 356
- Buildings
- 1
- Land
- 2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 208
- Rehab units
- 148
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 30% | 0% | 141 | |
| 100% | 30% | 0% | 141 | |
| 100% | 0% | 0% | 125 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400092
Projects with 150–800 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 4 yrs 4 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Dec 2028 | Jun 2027 |
| Concrete structure (RCC) | 30% | 48% |
| Units booked (free sale) | 68% | 70% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Inspira Aura, Borivali West
- Adarsh Garden Grove, Borivali West
- Sethia Marine View, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Inspira Aura | February 2024 | March 2029 | 13% | 87 units booked out of 124 units for sale |
| Adarsh Garden Grove | December 2022 | Dec 2026 – Dec 2028 | 48% | 106 units booked out of total 226 units |
| Sethia Marine View | November 2022 | June 2027 | 100% | 162 units booked out of total 179 units |
About this project
Shraddha Paradise by Shraddha Prime Projects Limited is a 356-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in August 2023 with possession due in December 2028. 141 units booked out of 208 units for sale. The concrete structure (RCC) is 30% complete.
Read full summary
Shraddha Paradise is a BMC-sanctioned project by Shraddha Prime Projects Limited in Borivali West, Mumbai 400092, registered with MahaRERA as P51800052244. It was launched in August 2023. It has 356 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 356 units, 208 are for sale and 148 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.
141 units booked out of 208 units for sale (68%).
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.