Mirai, Andheri West
by Graceunited Developers · Andheri West, Mumbai 400058 · Map
- Launched
- Aug 20233 yrs 7 mths promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 60%Mid-construction
- Booked
- 12 of 6518%
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 6
- 1 BHK
- 34
- 2 BHK
- 22
- 3 BHK
- 1
- Other units
- 2
- Total units
- 65
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 0% | 12 | |
| 100% | 60% | 0% | 12 | |
| 100% | 60% | 0% | 12 | |
| 90% | 0% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400058
Projects with 30–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 7 mths | 3 yrs 1 mth |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Mar 2027 | Dec 2027 |
| Concrete structure (RCC) | 60% | 95% |
| Units booked | 18% | 76% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Umar Park, Andheri West
- 5th Element, Andheri West
- Labh Sapphire, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Umar Park | November 2023 | June 2027 | 93% | 20 units booked out of 41 units for sale |
| 5th Element | May 2023 | October 2028 | 100% | 39 units booked out of 51 units for sale |
| Labh Sapphire | March 2024 | December 2027 | 95% | 16 units booked out of 19 units for sale |
About this project
Mirai by Graceunited Developers is a 65-unit SRA-sanctioned project in Andheri West, Mumbai 400058, launched in August 2023 with possession due in March 2027. 12 units booked out of total 65 units. The concrete structure (RCC) is 60% complete.
Read full summary
Mirai is an SRA-sanctioned project by Graceunited Developers in Andheri West, Mumbai 400058, registered with MahaRERA as P51800052327. It was launched in August 2023. It has 65 units in 2 buildings: 63 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.
12 units booked out of total 65 units (18%).