Labh Sapphire, Andheri West

by Labhartirealities · Andheri West, Mumbai 400058 · Map

Launched
Mar 20243 yrs 9 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
95%Mid-construction
Booked (free sale)
16 of 1984% · 48 rehab units
Buildings
30.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale16 booked out of 19 units

Rehab48 units for existing members

Total 67 units. Rehab units are not for sale.

Project facts

2 BHK
33
3 BHK
22
4 BHK
10
Other units
2
Total units
67
Buildings
3
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
19
Rehab units
48

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 95%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%16
100%90%0%16
100%0%0%5
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400058

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400058
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths3 yrs 2 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)Dec 2027Jun 2027
Concrete structure (RCC)95%90%
Units booked (free sale)84%34%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Labh Sapphire by Labhartirealities is a 67-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in March 2024 with possession due in December 2027. 16 units booked out of 19 units for sale. The concrete structure (RCC) is 95% complete.

Read full summary

Labh Sapphire is a BMC-sanctioned project by Labhartirealities in Andheri West, Mumbai 400058, registered with MahaRERA as P51800055284. It was launched in March 2024. It has 67 units in 3 buildings: 65 homes (2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 67 units, 19 are for sale and 48 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.

16 units booked out of 19 units for sale (84%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 90% to 95%.