Shagun Residency, Andheri West
by Shagun Construction · Andheri West, Mumbai 400058 · Map
- Launched
- Aug 20232 yrs 10 mths originally promised
- Possession (MahaRERA)
- Sep 2027Extended by 1 yr 3 mths
- Concrete structure
- 85%Mid-construction
- Booked (free sale)
- 22 of 2685% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale22 booked out of 26 units
Rehab16 units for existing members
Total 42 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 17
- 3 BHK
- 9
- Other units
- 16
- Total units
- 42
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 26
- Rehab units
- 16
- Reserved units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 85% | 10% | 22 | |
| 100% | 85% | 10% | 5 | |
| 100% | 80% | 0% | 1 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400058
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 3 yrs 9 mths |
| Possession date extended | By 1 yr 3 mths | 1 of 3 |
| Possession date (MahaRERA) | Sep 2027 | Jun 2027 |
| Concrete structure (RCC) | 85% | 93% |
| Units booked (free sale) | 85% | 37% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Integrated Kavya, Andheri West
- Umar Park, Andheri West
- Sanghvi Palazzo, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Integrated Kavya | September 2023 | June 2027 | 67% | 7 units booked out of 19 units for sale |
| Umar Park | November 2023 | June 2027 | 93% | 20 units booked out of 41 units for sale |
| Sanghvi Palazzo | December 2023 | December 2027 | 100% | 1 unit booked out of total 21 units |
About this project
Shagun Residency by Shagun Construction is a 42-unit SRA-sanctioned project in Andheri West, Mumbai 400058, launched in August 2023 with possession due in September 2027. 22 units booked out of 26 units for sale. The concrete structure (RCC) is 85% complete.
Read full summary
Shagun Residency is an SRA-sanctioned project by Shagun Construction in Andheri West, Mumbai 400058, registered with MahaRERA as P51800052339. It was launched in August 2023. It has 42 units in 1 building: 26 homes (2 and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 26 are for sale and 16 are rehab units for existing members.
Its registered possession date is September 2027, extended by 1 year 3 months from the original June 2026. Construction: excavation complete, structure (RCC) 85% complete, final finishes 10% complete.
22 units booked out of 26 units for sale (85%). Since the July 2026 update, 17 more units have been booked.