Avenue 9, Juhu
by Shree Mahavir Estates Tushar Bindu · Juhu, Mumbai 400049 · Map
- Launched
- Aug 20236 yrs 9 mths promised
- Possession (MahaRERA)
- May 2030Not extended
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 13 of 2454% · 26 rehab units
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale13 booked out of 24 units
Rehab26 units for existing members
Total 50 units. Rehab units are not for sale.
Project facts
- 3 BHK
- 40
- 4 BHK
- 10
- Total units
- 50
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 24
- Rehab units
- 26
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 15% | 13 | |
| 100% | 90% | 15% | 11 | |
| 100% | 50% | 0% | 10 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400049
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 9 mths | 3 yrs 6 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | May 2030 | Dec 2026 |
| Concrete structure (RCC) | 90% | 100% |
| Units booked (free sale) | 54% | 68% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Maestro, Juhu
- Rishabraj Trident, Juhu
- Gurukrupa Alaknanda, Juhu
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Maestro | May 2023 | November 2026 | 100% | 27 units booked out of total 35 units |
| Rishabraj Trident | November 2023 | August 2028 | 100% | 21 units booked out of 31 units for sale |
| Gurukrupa Alaknanda | November 2023 | December 2026 | 100% | 19 units booked out of 47 units for sale |
About this project
Avenue 9 by Shree Mahavir Estates Tushar Bindu is a 50-unit MHADA-sanctioned project in Juhu, Mumbai 400049, launched in August 2023 with possession due in May 2030. 13 units booked out of 24 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Avenue 9 is a MHADA-sanctioned project by Shree Mahavir Estates Tushar Bindu in Juhu, Mumbai 400049, registered with MahaRERA as P51800052372. It was launched in August 2023. It has 50 units in 2 buildings, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 50 units, 24 are for sale and 26 are rehab units for existing members.
Its registered possession date is May 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 15% complete.
13 units booked out of 24 units for sale (54%). Since the July 2026 update, 2 more units have been booked.