Rishabraj Trident, Juhu

by H Rishabraj Realty · Juhu, Mumbai 400049 · Map

Launched
Nov 20234 yrs 9 mths promised
Possession (MahaRERA)
Aug 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
21 of 3168% · 37 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale21 booked out of 31 units

Rehab37 units for existing members

Total 68 units. Rehab units are not for sale.

Project facts

1 BHK
1
2 BHK
32
3 BHK
23
4 BHK
9
5+ BHK
2
Other units
1
Total units
68
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
31
Rehab units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 5%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%21
100%5%0%17
100%5%0%17
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400049

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400049
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 9 mths3 yrs 6 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Aug 2028Jun 2027
Concrete structure (RCC)100%95%
Units booked (free sale)68%55%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Rishabraj Trident by H Rishabraj Realty is a 68-unit MHADA-sanctioned project in Juhu, Mumbai 400049, launched in November 2023 with possession due in August 2028. 21 units booked out of 31 units for sale. The concrete structure (RCC) is complete.

Read full summary

Rishabraj Trident is a MHADA-sanctioned project by H Rishabraj Realty in Juhu, Mumbai 400049, registered with MahaRERA as P51800053505. It was launched in November 2023. It has 68 units in 1 building: 67 homes (1, 2, 3, 4 and 5+ BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 68 units, 31 are for sale and 37 are rehab units for existing members.

Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

21 units booked out of 31 units for sale (68%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 5% to 100%.

Rishabraj's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA43
Total units across these projects1,514
Completed without extending the possession date22
Completed after an extension3
Lapsed3
Under construction15
Possession date extended on the builder's application4
Typical time from launch to 100% structure2 years 9 months
MahaRERA complaints (filed by or against the builder), all Rishabraj projects33 (4 of 43 projects)

See all Rishabraj projects →