Second Avenue Phase 1, Andheri East

Lapsed

by Atul Projects Realty Private Limited · Andheri East, Mumbai 400093 · Map

Launched
Aug 20232 yrs 4 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
90%Mid-construction
Booked
–
Buildings
11.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
51
Total units
51
Buildings
1
Land
1.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 25%Dec 2025: Final finishes 25%Jul 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 90%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%25%–
100%90%25%–
100%90%25%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Second Avenue Phase 1 by Atul Projects Realty Private Limited is a 51-unit BMC-sanctioned project in Andheri East, Mumbai 400093, launched in August 2023; its MahaRERA registration has lapsed. The concrete structure (RCC) is 90% complete.

Read full summary

Second Avenue Phase 1 is a BMC-sanctioned project by Atul Projects Realty Private Limited in Andheri East, Mumbai 400093, registered with MahaRERA as P51800052424. It was launched in August 2023. It has 51 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes 25% complete.