Vikhroli ASPI Project, Vikhroli

by Lodha Developers Limited · Vikhroli, Mumbai 400079 · Map

Launched
Oct 2023First of 4 phases
Possession (MahaRERA)
Jan 2029 – Dec 2030Extended in all 4 phases
Concrete structure
55%Weighted across 4 phases
Booked
323 of 48866% · 316 in Jul 2026
Buildings
40.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
11
3 BHK
466
4 BHK
1
Other units
10
Total units
488
Buildings
4
Land
0.8 acres
Phases
4
MahaRERA complaints
0

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Vikhroli ASPI Project 1
Mid-construction
P5180005307213250%73%
Vikhroli ASPI Project 3
Mid-construction
P5180005325313458%63%
Vikhroli ASPI Project 2
Nearing possession
P5180005437579100%91%
Vikhroli ASPI Project 4
Mid-construction
P5180007849013331%48%
Show updates by phase

Vikhroli ASPI Project 1 (P51800053072)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%98
100%50%0%96
100%35%0%87
100%0%0%68

"–" means MahaRERA shows no figure for that update.

Vikhroli ASPI Project 3 (P51800053253)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%58%0%86
100%58%0%85
100%35%0%80
100%0%0%31

"–" means MahaRERA shows no figure for that update.

Vikhroli ASPI Project 2 (P51800054375)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%74
100%78%0%70
100%30%0%63
100%0%0%0

"–" means MahaRERA shows no figure for that update.

Vikhroli ASPI Project 4 (P51800078490)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%31%0%65
100%6%0%65
75%0%0%39
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)55%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 72%Dec 2025: Excavation 93%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 24%Jul 2026: Concrete structure (RCC) 45%Oct 2026: Concrete structure (RCC) 55%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 55%Final finishes 0%

How to read construction stages

About this project

Vikhroli ASPI Project by Lodha Developers Limited is a 488-unit SRA-sanctioned project in Vikhroli, Mumbai 400079, registered with MahaRERA in 4 phases, with possession dates from January 2029 to December 2030. 323 units booked out of total 488 units. The concrete structure (RCC) is 55% complete.

Read full summary

Vikhroli ASPI Project is an SRA-sanctioned project by Lodha Developers Limited in Vikhroli, Mumbai 400079, registered with MahaRERA as 4 phases (P51800053072, P51800053253, P51800054375, P51800078490). The first phase was launched in October 2023. Together the phases have 488 units in 4 buildings: 478 homes (2, 3 and 4 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. All 4 phases are active on MahaRERA.

The phases' registered possession dates run from January 2029 to December 2030; all 4 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 55% complete and final finishes 0% complete. 1 of the 4 phases has its structure complete.

323 units booked out of total 488 units (66%). Since the July 2026 update, 7 more units have been booked.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →