Ocean Breeze, Kandivali West

by Bhairav Smile Infraprojects · Kandivali West, Mumbai 400067 · Map

Launched
Oct 20234 yrs 11 mths promised
Possession (MahaRERA)
Sep 2028Not extended
Concrete structure
65%Mid-construction
Booked (free sale)
85 of 10779% · 48 rehab units
Buildings
30.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale85 booked out of 107 units

Rehab48 units for existing members

Total 155 units. Rehab units are not for sale.

Project facts

1 BHK
89
2 BHK
53
3 BHK
13
Total units
155
Buildings
3
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
107
Rehab units
48

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)65%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 65%Oct 2026: Concrete structure (RCC) 65%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 60%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 65%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%65%60%85
100%65%60%68
0%0%0%66
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths3 yrs 6 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Sep 2028Jun 2027
Concrete structure (RCC)65%82%
Units booked (free sale)79%71%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ocean Breeze by Bhairav Smile Infraprojects is a 155-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in October 2023 with possession due in September 2028. 85 units booked out of 107 units for sale. The concrete structure (RCC) is 65% complete.

Read full summary

Ocean Breeze is a MHADA-sanctioned project by Bhairav Smile Infraprojects in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800053078. It was launched in October 2023. It has 155 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 155 units, 107 are for sale and 48 are rehab units for existing members.

Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 65% complete, final finishes 60% complete.

85 units booked out of 107 units for sale (79%). Since the July 2026 update, 17 more units have been booked.