Dps Nakshatra Heights, Kandivali West
Ready to moveLapsed
by Dpspro Dev LLP · Kandivali West, Mumbai 400067 · Map
- Launched
- Sep 20232 yrs 9 mths promised
- Possession (MahaRERA)
- Jun 2026Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 109 of 13978% · 52 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale109 booked out of 139 units
Rehab52 units for existing members
Total 191 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 36
- 2 BHK
- 58
- 3 BHK
- 77
- 4 BHK
- 2
- Other units
- 16
- Total units
- 191
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 139
- Rehab units
- 52
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 109 | |
| 100% | 100% | 85% | 100 | |
| 100% | 90% | 0% | 87 | |
| 100% | 31% | 0% | 16 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 4 yrs 7 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Jun 2026 | Feb 2028 |
| Concrete structure (RCC) | 100% | 65% |
| Units booked (free sale) | 78% | 71% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Ocean Breeze, Kandivali West
- Sai Elegance, Kandivali West
- Shreeji Gateway, Kandivali West
- Olive, Kandivali West
- Arthaya, Kandivali West
- Charkop Rakesh Co. Op. Hsg. Soceity Ltd, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ocean Breeze | October 2023 | September 2028 | 65% | 85 units booked out of 107 units for sale |
| Sai Elegance | October 2023 | September 2026 | 21% | 60 units booked out of 85 units for sale |
| Shreeji Gateway | October 2023 | December 2028 | 0% | – |
| Olive | November 2023 | December 2027 | 70% | 113 units booked out of total 151 units |
| Arthaya | July 2023 | April 2028 | 95% | 58 units booked out of 131 units for sale |
| Charkop Rakesh Co. Op. Hsg. Soceity Ltd | July 2023 | December 2027 | 65% | 17 units booked out of 52 units for sale |
About this project
Dps Nakshatra Heights by Dpspro Dev LLP is a 191-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in September 2023; its MahaRERA registration has lapsed. 109 units booked out of 139 units for sale. The concrete structure (RCC) is complete.
Read full summary
Dps Nakshatra Heights is a MHADA-sanctioned project by Dpspro Dev LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800052649. It was launched in September 2023. It has 191 units in 2 buildings: 175 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 191 units, 139 are for sale and 52 are rehab units for existing members.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
109 units booked out of 139 units for sale (78%). Since the July 2026 update, 9 more units have been booked.