Vira Villa, Vile Parle East
by Vira Realty · Vile Parle East, Mumbai 400057 · Map
- Launched
- Oct 20234 yrs 5 mths promised
- Possession (MahaRERA)
- Mar 2028Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 12 of 1392% · 8 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 13 units
Rehab8 units for existing members
Total 21 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 10
- 3 BHK
- 4
- 4 BHK
- 1
- Other units
- 5
- Total units
- 21
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 13
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 12 | |
| 100% | 45% | 0% | – | |
| 100% | 45% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400057
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 5 mths | 3 yrs 2 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Mar 2028 | Oct 2026 |
| Concrete structure (RCC) | 100% | 98% |
| Units booked (free sale) | 92% | 76% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Aventus Erica, Vile Parle East
- Viva Dhanlaxmi, Vile Parle East
- Archis, Vile Parle East
- Sheetal Surya Prakash, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Aventus Erica | October 2023 | December 2027 | 95% | 11 units booked out of 12 units for sale |
| Viva Dhanlaxmi | November 2023 | August 2026 | 100% | 14 units booked out of 23 units for sale |
| Archis | July 2023 | September 2025 | 100% | 9 units booked out of 9 units for sale |
| Sheetal Surya Prakash | April 2023 | December 2026 | 0% | 20 units booked out of total 38 units |
About this project
Vira Villa by Vira Realty is a 21-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in October 2023 with possession due in March 2028. 12 units booked out of 13 units for sale. The concrete structure (RCC) is complete.
Read full summary
Vira Villa is a BMC-sanctioned project by Vira Realty in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800053187. It was launched in October 2023. It has 21 units in 1 building: 16 homes (1, 2, 3 and 4 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 13 are for sale and 8 are rehab units for existing members.
Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
12 units booked out of 13 units for sale (92%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 45% to 100%.