Skip to main content

Viva Dhanlaxmi, Vile Parle East

Ready to move

by Y K & Sons Mumbai · Vile Parle East, Mumbai 400057 · Map

Launched
Nov 20232 yrs 9 mths promised
Possession (MahaRERA)
Aug 2026Not extended
Concrete structure
100%Ready to move
Booked (free sale)
14 of 2361%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 23 units

Land-owner share9 units, not for sale

Total 32 units. Land-owner units are not for sale.

Project facts

2 BHK
12
3 BHK
9
Other units
11
Total units
32
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
23
Land-owner share (not for sale)
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 95%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%14
100%95%0%13
100%90%0%13
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400057

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths4 yrs 2 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)Aug 2026Dec 2027
Concrete structure (RCC)100%100%
Units booked (free sale)61%100%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Viva Dhanlaxmi by Y K & Sons Mumbai is a 32-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in November 2023 with possession due in August 2026. 14 units booked out of 23 units for sale. The concrete structure (RCC) is complete.

Read full summary

Viva Dhanlaxmi is a BMC-sanctioned project by Y K & Sons Mumbai in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800053647. It was launched in November 2023. It has 32 units in 1 building: 21 homes (2 and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 32 units, 23 are for sale and 9 are the land-owner's share, not for sale.

Possession was due in August 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

14 units booked out of 23 units for sale (61%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 95% to 100%.