Serenity Decks, Goregaon East
by Eternity And Aakar Realty · Goregaon East, Mumbai 400063 · Map
- Launched
- Oct 20234 yrs 9 mths promised
- Possession (MahaRERA)
- Jul 2028Not extended
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 18 of 18100% · 19 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale18 booked out of 18 units
Rehab19 units for existing members
Total 37 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 1
- 2 BHK
- 21
- 3 BHK
- 10
- Other units
- 4
- Total units
- 37
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 18
- Rehab units
- 19
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 0% | 18 | |
| 100% | 80% | 0% | 18 | |
| 100% | 80% | 0% | 19 | |
| 100% | 40% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400063
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 9 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Jul 2028 | Jul 2026 |
| Concrete structure (RCC) | 80% | 45% |
| Units booked (free sale) | 100% | 25% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Pandurangwadi Laxmi Niwas Chsl, Goregaon East
- Shantprabha Co Operative Housing Society Limited, Goregaon East
- Vira One, Goregaon East
- Padmanabh Apartment Co-Operative Housing Society Ltd, Goregaon East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pandurangwadi Laxmi Niwas Chsl | November 2023 | March 2026 | 0% | 1 unit booked out of 17 units for sale |
| Shantprabha Co Operative Housing Society Limited | September 2023 | June 2027 | 0% | 15 units booked out of total 41 units |
| Vira One | January 2024 | December 2026 | 90% | 25 units booked out of 28 units for sale |
| Padmanabh Apartment Co-Operative Housing Society Ltd | April 2023 | December 2025 | 100% | 3 units booked out of total 23 units |
About this project
Serenity Decks by Eternity And Aakar Realty is a 37-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in October 2023 with possession due in July 2028. 18 units booked out of 18 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Serenity Decks is a BMC-sanctioned project by Eternity And Aakar Realty in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800053216. It was launched in October 2023. It has 37 units in 1 building: 33 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 37 units, 18 are for sale and 19 are rehab units for existing members.
Its registered possession date is July 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.
18 units booked out of 18 units for sale (100%).