Skip to main content

Vira One, Goregaon East

by Grow More Builders And Developers Private Limited · Goregaon East, Mumbai 400063 · Map

Launched
Jan 20242 yrs 11 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
90%Mid-construction
Booked (free sale)
25 of 2889% · 12 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale25 booked out of 28 units

Rehab12 units for existing members

Total 40 units. Rehab units are not for sale.

Project facts

1 BHK
22
2 BHK
8
3 BHK
3
4 BHK
1
Other units
6
Total units
40
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
28
Rehab units
12
Reserved units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services35%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 35%Jul 2026: Final finishes 35%Oct 2026: Final finishes 35%Excavation 100%Concrete structure (RCC) 90%Final finishes 35%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%35%25
100%90%35%25
100%50%35%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400063

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400063
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths3 yrs 5 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2026May 2027
Concrete structure (RCC)90%8%
Units booked (free sale)89%37%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vira One by Grow More Builders And Developers Private Limited is a 40-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in January 2024 with possession due in December 2026. 25 units booked out of 28 units for sale. The concrete structure (RCC) is 90% complete.

Read full summary

Vira One is a BMC-sanctioned project by Grow More Builders And Developers Private Limited in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800054485. It was launched in January 2024. It has 40 units in 1 building: 34 homes (1, 2, 3 and 4 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 40 units, 28 are for sale and 12 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 35% complete.

25 units booked out of 28 units for sale (89%).