Unique Residency Vikarharta, Vikhroli

by Fazal Mehmood Shaikh · Vikhroli, Mumbai 400083 · Map

Launched
Oct 20233 yrs 10 mths promised
Possession (MahaRERA)
Aug 2027Not extended
Concrete structure
42%Mid-construction
Booked
79 of 14256%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
67
2 BHK
66
Other units
9
Total units
142
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)42%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 42%Dec 2025: Concrete structure (RCC) 42%Jul 2026: Concrete structure (RCC) 42%Oct 2026: Concrete structure (RCC) 42%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 42%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%42%0%79
100%42%0%–
100%42%0%–
100%42%0%79

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400083

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths3 yrs 2 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Aug 2027Jun 2027
Concrete structure (RCC)42%85%
Units booked56%78%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Unique Residency Vikarharta by Fazal Mehmood Shaikh is a 142-unit project in Vikhroli, Mumbai 400083, launched in October 2023 with possession due in August 2027. 79 units booked out of total 142 units. The concrete structure (RCC) is 42% complete.

Read full summary

Unique Residency Vikarharta is a project by Fazal Mehmood Shaikh in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800053298. It was launched in October 2023. It has 142 units in 1 building: 133 homes (1 and 2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 42% complete, final finishes not started.

79 units booked out of total 142 units (56%).