Pragati Pinnacle, Vikhroli
by Pragati Developers · Vikhroli, Mumbai 400083 · Map
- Launched
- Nov 20233 yrs 1 mth promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 74 of 9479% · 40 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale74 booked out of 94 units
Rehab40 units for existing members
Total 134 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 57
- 2 BHK
- 63
- Other units
- 14
- Total units
- 134
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 94
- Rehab units
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 60% | 74 | |
| 50% | 48% | 25% | 73 | |
| 50% | 45% | 13% | 67 | |
| 100% | 60% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400083
Projects with 60–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 1 mth | 3 yrs 6 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Oct 2027 |
| Concrete structure (RCC) | 95% | 58% |
| Units booked (free sale) | 79% | 77% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- The Grand, Vikhroli
- Unique Residency Vikarharta, Vikhroli
- Shubhamkaroti Aarambh, Vikhroli
- Gurukrupa Darshanam, Vikhroli
- Suji Platinum, Vikhroli
- Natasha Avana, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The Grand | October 2023 | December 2026 | 0% | 33 units booked out of total 129 units |
| Unique Residency Vikarharta | October 2023 | August 2027 | 42% | 79 units booked out of total 142 units |
| Shubhamkaroti Aarambh | October 2023 | December 2027 | 75% | 61 units booked out of 78 units for sale |
| Gurukrupa Darshanam | October 2023 | December 2026 | 100% | 94 units booked out of 111 units for sale |
| Suji Platinum | October 2023 | December 2027 | 0% | 94 units booked out of 123 units for sale |
| Natasha Avana | December 2023 | December 2028 | 100% | 46 units booked out of 58 units for sale |
About this project
Pragati Pinnacle by Pragati Developers is a 134-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in November 2023 with possession due in December 2026. 74 units booked out of 94 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Pragati Pinnacle is a MHADA-sanctioned project by Pragati Developers in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800053467. It was launched in November 2023. It has 134 units in 1 building: 120 homes (1 and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 134 units, 94 are for sale and 40 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes 60% complete.
74 units booked out of 94 units for sale (79%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 48% to 95%.