Skip to main content

Edmont - Aurelia, Kandivali West

by Sheth Homes Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
Nov 20235 yrs 9 mths promised
Possession (MahaRERA)
Aug 2029Not extended
Concrete structure
0%Early stage
Booked
140 of 37837% · 138 in Jul 2026
Buildings
10.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
2
2 BHK
183
3 BHK
181
Other units
12
Total units
378
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%140
100%0%0%138
100%0%0%119
0%0%0%84

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400067

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 9 mths5 yrs 4 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Aug 2029Dec 2028
Concrete structure (RCC)0%18%
Units booked37%44%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Edmont - Aurelia by Sheth Homes Private Limited is a 378-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in November 2023 with possession due in August 2029. 140 units booked out of total 378 units. Work on the concrete structure (RCC) has not started.

Read full summary

Edmont - Aurelia is a BMC-sanctioned project by Sheth Homes Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800053546. It was launched in November 2023. It has 378 units in 1 building: 366 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

140 units booked out of total 378 units (37%). Since the July 2026 update, 2 more units have been booked.