ShreejiAikyam, Kandivali West

by Rushabh Developers · Kandivali West, Mumbai 400067 · Map

Launched
Jun 20235 yrs 6 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
220 of 41353% · 24 rehab units
Buildings
32.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale220 booked out of 413 units

Rehab24 units for existing members

Total 437 units. Rehab units are not for sale.

Project facts

2 BHK
122
3 BHK
127
4 BHK
33
Other units
155
Total units
437
Buildings
3
Land
2.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
413
Rehab units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation87%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 87%Oct 2026: Excavation 87%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 87%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
87%0%0%220
87%0%0%204
0%0%0%154
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 6 mths4 yrs 10 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2028Feb 2028
Concrete structure (RCC)0%48%
Units booked (free sale)53%45%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

ShreejiAikyam by Rushabh Developers is a 437-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in June 2023 with possession due in December 2028. 220 units booked out of 413 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

ShreejiAikyam is an SRA-sanctioned project by Rushabh Developers in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800051233. It was launched in June 2023. It has 437 units in 3 buildings: 282 homes (2, 3 and 4 BHK) and 155 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 437 units, 413 are for sale and 24 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation 87% complete, structure (RCC) not started, final finishes not started.

220 units booked out of 413 units for sale (53%). Since the July 2026 update, 16 more units have been booked.