by Krishna Developers · Malad West, Mumbai 400064 · Map

Launched
Dec 20231 yr 3 mths promised
Possession (MahaRERA)
Mar 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
1 of 195%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
4
2 BHK
2
Other units
13
Total units
19
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 25%Dec 2025: Final finishes 25%Jul 2026: Final finishes 25%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%1
100%100%25%–
100%100%25%–
100%100%25%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Disha Darshan by Krishna Developers is a 19-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in December 2023; its MahaRERA registration has lapsed. 1 unit booked out of total 19 units. The concrete structure (RCC) is complete.

Read full summary

Disha Darshan is a BMC-sanctioned project by Krishna Developers in Malad West, Mumbai 400064, registered with MahaRERA as P51800053854. It was launched in December 2023. It has 19 units in 1 building: 6 homes (1 and 2 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.

1 unit booked out of total 19 units (5%).