Varella Mansion, Borivali West
by Dean Home LLP · Borivali West, Mumbai 400103 · Map
- Launched
- Dec 20233 yrs 10 mths promised
- Possession (MahaRERA)
- Oct 2027Not extended
- Concrete structure
- 40%Mid-construction
- Booked (free sale)
- 12 of 6419% · 18 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 64 units
Rehab18 units for existing members
Total 82 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 31
- 2 BHK
- 34
- 3 BHK
- 17
- Total units
- 82
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 64
- Rehab units
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 40% | 0% | 12 | |
| 100% | 40% | 0% | 8 | |
| 100% | 35% | 0% | 4 | |
| 100% | 10% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400103
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 3 yrs 10 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | Oct 2027 | Dec 2027 |
| Concrete structure (RCC) | 40% | 100% |
| Units booked (free sale) | 19% | 64% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Kamla Borivali Lucky, Borivali West
- Devki Nagar Chs Ltd, Borivali West
- The Erica, Borivali West
- 103 West, Borivali West
- Verve Elina, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kamla Borivali Lucky | October 2023 | December 2027 | 100% | 40 units booked out of 47 units for sale |
| Devki Nagar Chs Ltd | February 2024 | December 2027 | 30% | 70 units booked out of total 110 units |
| The Erica | May 2024 | March 2028 | 100% | 19 units booked out of 30 units for sale |
| 103 West | June 2024 | March 2029 | 100% | 42 units booked out of 64 units for sale |
| Verve Elina | April 2023 | December 2026 | 83% | 37 units booked out of total 68 units |
About this project
Varella Mansion by Dean Home LLP is an 82-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in December 2023 with possession due in October 2027. 12 units booked out of 64 units for sale. The concrete structure (RCC) is 40% complete.
Read full summary
Varella Mansion is a BMC-sanctioned project by Dean Home LLP in Borivali West, Mumbai 400103, registered with MahaRERA as P51800053911. It was launched in December 2023. It has 82 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 82 units, 64 are for sale and 18 are rehab units for existing members.
Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.
12 units booked out of 64 units for sale (19%). Since the July 2026 update, 4 more units have been booked.