Skip to main content

Kamla Borivali Lucky, Borivali West

Ready to move

by Kamla Homes and Lifestyles Private Limited · Borivali West, Mumbai 400103 · Map

Launched
Oct 20234 yrs 2 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
40 of 4785% · 60 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale40 booked out of 47 units

Rehab60 units for existing members

Total 107 units. Rehab units are not for sale.

Project facts

1 BHK
16
2 BHK
63
3 BHK
14
Other units
14
Total units
107
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
47
Rehab units
60

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%40
100%100%0%29
100%80%0%20
100%40%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400103

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400103
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths3 yrs 10 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2027Sep 2027
Concrete structure (RCC)100%62%
Units booked (free sale)85%48%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Kamla Borivali Lucky by Kamla Homes and Lifestyles Private Limited is a 107-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in October 2023 with possession due in December 2027. 40 units booked out of 47 units for sale. The concrete structure (RCC) is complete.

Read full summary

Kamla Borivali Lucky is a BMC-sanctioned project by Kamla Homes and Lifestyles Private Limited in Borivali West, Mumbai 400103, registered with MahaRERA as P51800053037. It was launched in October 2023. It has 107 units in 1 building: 93 homes (1, 2 and 3 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 107 units, 47 are for sale and 60 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

40 units booked out of 47 units for sale (85%). Since the July 2026 update, 11 more units have been booked.