Arkade Pearl, Vile Parle East
by Arkade Developers Limited · Vile Parle East, Mumbai 400057 · Map
- Launched
- Jan 2024First of 4 phases
- Possession (MahaRERA)
- Dec 2026 – Jun 2027Not extended
- Concrete structure
- 99%Weighted across 4 phases
- Booked (free sale)
- 70 of 8582% · 75 rehab units
- Buildings
- 61 acre
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale70 booked out of 85 units
Rehab75 units for existing members
Total 160 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 16
- 2 BHK
- 105
- 3 BHK
- 39
- Total units
- 160
- Buildings
- 6
- Land
- 1 acre
- Phases
- 4
- MahaRERA complaints
- 0
- Free-sale units
- 85
- Rehab units
- 75
The 4 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Arkade Pearl 1 Ready to move | P51800054195 | 88 | 100% | 41% | |
| Arkade Pearl 2 Nearing possession | P51800077017 | 32 | 100% | 41% | |
| Arkade Pearl 3 Completed | P51800078295 | 24 | 100% | 62% | |
| Arkade Pearl 4 Mid-construction | P51800079922 | 16 | 89% | 38% |
Show updates by phase
Arkade Pearl 1 (P51800054195)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 36 | |
| 100% | 100% | 71% | 34 | |
| 100% | 100% | 10% | 30 | |
| 100% | 41% | 6% | 17 |
"–" means MahaRERA shows no figure for that update.
Arkade Pearl 2 (P51800077017)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 89% | 13 | |
| 100% | 100% | 76% | 13 | |
| 100% | 100% | 34% | 12 | |
| 100% | 89% | 11% | 7 |
"–" means MahaRERA shows no figure for that update.
Arkade Pearl 3 (P51800078295)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 15 | |
| 100% | 100% | 74% | 15 | |
| 100% | 100% | 4% | 11 | |
| 100% | 11% | 3% | 2 |
"–" means MahaRERA shows no figure for that update.
Arkade Pearl 4 (P51800079922)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 89% | 0% | 6 | |
| 100% | 33% | 0% | 5 | |
| 90% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Arkade Pearl by Arkade Developers Limited is a 160-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, registered with MahaRERA in 4 phases, with possession dates from December 2026 to June 2027. 70 units booked out of 85 units for sale. The concrete structure (RCC) is 99% complete.
Read full summary
Arkade Pearl is a BMC-sanctioned project by Arkade Developers Limited in Vile Parle East, Mumbai 400057, registered with MahaRERA as 4 phases (P51800054195, P51800077017, P51800078295, P51800079922). The first phase was launched in January 2024. Together the phases have 160 units in 6 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 3 are active and 1 is completed. Of the 160 units, 85 are for sale and 75 are rehab units for existing members.
The phases' registered possession dates run from December 2026 to June 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 99% complete and final finishes 88% complete. 3 of the 4 phases have their structure complete.
70 units booked out of 85 units for sale (82%). Since the July 2026 update, 3 more units have been booked.
Arkade's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 27 |
|---|---|
| Total units across these projects | 3,356 |
| Completed without extending the possession date | 14 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 1 |
| Typical time from launch to 100% structure | 3 years 8 months |
| MahaRERA complaints (filed by or against the builder), all Arkade projects | 15 (6 of 27 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.