Arkade projects in Mumbai

MahaRERA projects by Arkade registered 2017–2026 in Mumbai.

Projects registered with MahaRERA27
Total units across these projects3,356
Full record

MahaRERA projects registered 2017–2026 in Mumbai

Completed without extending the possession date14
Completed after an extension0
Lapsed3
Under construction10
Possession date extended on the builder's application1
Typical time from launch to 100% structure3 years 8 months
MahaRERA complaints (filed by or against the builder), all Arkade projects15 (6 of 27 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Bhandup East (8) · Malad West (3) · Goregaon East (3) · Vile Parle East (2) · Santacruz West (2) · Borivali West (1) · Andheri East (1) · Mulund West (1) · Bhandup West (1) · Cumballa Hill (1)

Under construction

ProjectVillageStagePossessionBooked
Arkade AscendMalad WestEarly stageOctober 20311 unit booked out of 165 units for sale
Arkade EvokeGoregaon WestEarly stageJune 202919 units booked out of 48 units for sale
Arkade NestMulund WestMid-constructionJune 2027268 units booked out of total 351 units
Arkade Pearl · 4 phasesVile Parle EastMid-constructionDec 2026 – Jun 202770 units booked out of 85 units for sale
Arkade RareBhandup WestMid-constructionDecember 2028333 units booked out of total 479 units
Arkade SapphireSantacruz WestEarly stageSeptember 20296 units booked out of 31 units for sale
Arkade ViewsGoregaon EastMid-constructionDecember 202719 units booked out of 21 units for sale
Arkade VistasGoregaon EastMid-constructionDecember 202772 units booked out of 84 units for sale
Completed
ProjectVillageStatus
Arkade AspireGoregaon EastCompleted
Arkade AuraSantacruz WestCompleted
Arkade CrownBorivali WestCompleted
Arkade EarthBhandup EastCompleted
Arkade Earth-DaffodilBhandup EastCompleted
Arkade EdenMalad WestCompleted
Arkade PrimeAndheri EastCompleted
Arkade RiseCumballa HillCompleted
Arkade SereneMalad WestCompleted
DarshanVile Parle EastCompleted
Lapsed
ProjectVillageStatus
Arkade Earth- BluebellBhandup EastLapsed
Arkade Earth-AspenBhandup EastLapsed
Arkade Earth-CarnationBhandup EastLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.