Chidakash, Chembur

by Yashvi Corporation · Chembur, Mumbai 400071 · Map

Launched
Jan 20242 yrs 11 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
60%Mid-construction
Booked
4 of 1429%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
3
3 BHK
9
5+ BHK
2
Total units
14
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%4
100%60%0%4
0%0%0%4
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths2 yrs 10 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Dec 2026Jan 2027
Concrete structure (RCC)60%90%
Units booked29%35%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Chidakash by Yashvi Corporation is a 14-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in January 2024 with possession due in December 2026. 4 units booked out of total 14 units. The concrete structure (RCC) is 60% complete.

Read full summary

Chidakash is a BMC-sanctioned project by Yashvi Corporation in Chembur, Mumbai 400071, registered with MahaRERA as P51800054316. It was launched in January 2024. It has 14 units in 1 building, with 2, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

4 units booked out of total 14 units (29%).