Vishwa Bhuvan, Chembur

Ready to move

by Majestic Royale City Developers · Chembur, Mumbai 400071 · Map

Launched
Oct 20232 yrs 5 mths originally promised
Possession (MahaRERA)
Mar 2027Extended by 1 yr
Concrete structure
100%Ready to move
Booked (free sale)
6 of 875% · 12 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale6 booked out of 8 units

Rehab12 units for existing members

Total 20 units. Rehab units are not for sale.

Project facts

2 BHK
15
3 BHK
5
Total units
20
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
8
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 95%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 10%Dec 2025: Final finishes 70%Jul 2026: Final finishes 70%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%6
100%100%70%0
100%100%70%0
100%95%10%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 10–40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths2 yrs 11 mths
Possession date extendedBy 1 yr3 of 6
Possession date (MahaRERA)Mar 2027Dec 2026
Concrete structure (RCC)100%90%
Units booked (free sale)75%32%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vishwa Bhuvan by Majestic Royale City Developers is a 20-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in October 2023 with possession due in March 2027. 6 units booked out of 8 units for sale. The concrete structure (RCC) is complete.

Read full summary

Vishwa Bhuvan is a BMC-sanctioned project by Majestic Royale City Developers in Chembur, Mumbai 400071, registered with MahaRERA as P51800053266. It was launched in October 2023. It has 20 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 20 units, 8 are for sale and 12 are rehab units for existing members.

Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

6 units booked out of 8 units for sale (75%). Since the July 2026 update, 6 more units have been booked and the possession date has moved from March 2026 to March 2027.