Skip to main content

Cullinan, Versova

by Lodha Developers Limited · Versova, Mumbai 400061 · Map

Launched
Jan 20244 yrs 11 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Nearing possession
Booked
5 of 4112%
Buildings
11.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
36
5+ BHK
3
Other units
2
Total units
41
Buildings
1
Land
1.9 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services8%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 48%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 8%Excavation 100%Concrete structure (RCC) 100%Final finishes 8%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%8%5
100%48%0%5
100%25%0%5
50%0%0%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Cullinan by Lodha Developers Limited is a 41-unit BMC-sanctioned project in Versova, Mumbai 400061, launched in January 2024 with possession due in December 2028. 5 units booked out of total 41 units. The concrete structure (RCC) is complete.

Read full summary

Cullinan is a BMC-sanctioned project by Lodha Developers Limited in Versova, Mumbai 400061, registered with MahaRERA as P51800054551. It was launched in January 2024. It has 41 units in 1 building: 39 homes (4 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 8% complete.

5 units booked out of total 41 units (12%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 48% to 100%.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →