Sigma Jade, Jogeshwari West

by Niketan Ventures Private Limited · Jogeshwari West, Mumbai 400102 · Map

Launched
Feb 20242 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2028Extended by 2 yrs
Concrete structure
9%Mid-construction
Booked
183 of 22083% · 54 in Jul 2026
Buildings
31.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
169
2 BHK
42
3 BHK
2
Other units
7
Total units
220
Buildings
3
Land
1.9 acres
Phases
1
MahaRERA complaints
0
Reserved units
30

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)9%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 75%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 9%Oct 2026: Concrete structure (RCC) 9%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 9%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%9%0%183
100%9%0%54
100%0%0%29
75%0%0%92

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400102

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths4 yrs 6 mths
Possession date extendedBy 2 yrs0 of 3
Possession date (MahaRERA)Dec 2028Dec 2028
Concrete structure (RCC)9%100%
Units booked83%91%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Sigma Jade by Niketan Ventures Private Limited is a 220-unit MMRDA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in February 2024 with possession due in December 2028. 183 units booked out of total 220 units. The concrete structure (RCC) is 9% complete.

Read full summary

Sigma Jade is an MMRDA-sanctioned project by Niketan Ventures Private Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800054626. It was launched in February 2024. It has 220 units in 3 buildings: 213 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, extended by 2 years from the original December 2026. Construction: excavation complete, structure (RCC) 9% complete, final finishes not started.

183 units booked out of total 220 units (83%). Since the July 2026 update, 129 more units have been booked.