- Launched
- Feb 20243 yrs 2 mths promised
- Possession (MahaRERA)
- Apr 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 16 of 1889% · 15 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale16 booked out of 18 units
Rehab15 units for existing members
Total 33 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 32
- 3 BHK
- 1
- Total units
- 33
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 18
- Rehab units
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 16 | |
| 100% | 100% | 80% | 15 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 2 yrs 10 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Apr 2027 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 89% | 35% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shankar Darshan Chs Ltd, Chembur
- Insignia, Chembur
- Kedarnath Apartments, Chembur
- Om Niwas, Chembur
- Manshaya Apartments, Chembur
- Parsn Bhagyalakshmi, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shankar Darshan Chs Ltd | March 2024 | December 2026 | 100% | 7 units booked out of 20 units for sale |
| Insignia | January 2024 | December 2026 | 100% | 7 units booked out of total 20 units |
| Kedarnath Apartments | April 2024 | December 2027 | 100% | 7 units booked out of 11 units for sale |
| Om Niwas | April 2024 | December 2026 | 90% | – |
| Manshaya Apartments | November 2023 | December 2026 | 85% | 0 units booked out of total 27 units |
| Parsn Bhagyalakshmi | October 2023 | May 2027 | 100% | 17 units booked out of 19 units for sale |
About this project
Pardis Shingadia by Pardis Shivansh LLP is a 33-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in February 2024 with possession due in April 2027. 16 units booked out of 18 units for sale. The concrete structure (RCC) is complete.
Read full summary
Pardis Shingadia is a BMC-sanctioned project by Pardis Shivansh LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800054651. It was launched in February 2024. It has 33 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 33 units, 18 are for sale and 15 are rehab units for existing members.
Its registered possession date is April 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
16 units booked out of 18 units for sale (89%). Since the July 2026 update, 1 more unit has been booked.