Parsn Bhagyalakshmi, Chembur
by Parsn Lifespaces · Chembur, Mumbai 400071 · Map
- Launched
- Oct 20232 yrs 9 mths originally promised
- Possession (MahaRERA)
- May 2027Extended by 10 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 17 of 1989%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale17 booked out of 19 units
Land-owner share13 units, not for sale
Total 32 units. Land-owner units are not for sale.
Project facts
- 2 BHK
- 32
- Total units
- 32
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 19
- Land-owner share (not for sale)
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 17 | |
| 100% | 88% | 0% | 14 | |
| 100% | 56% | 0% | 13 | |
| 100% | 56% | 0% | 10 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 3 yrs 2 mths |
| Possession date extended | By 10 mths | 3 of 6 |
| Possession date (MahaRERA) | May 2027 | Jan 2027 |
| Concrete structure (RCC) | 100% | 90% |
| Units booked (free sale) | 89% | 37% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Vishwa Bhuvan, Chembur
- Arihant Sky, Chembur
- Sai Signature, Chembur
- Manshaya Apartments, Chembur
- Pardis Shingadia, Chembur
- Ambal Parijath Chsl, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vishwa Bhuvan | October 2023 | March 2027 | 100% | 6 units booked out of 8 units for sale |
| Arihant Sky | October 2023 | December 2026 | 0% | 16 units booked out of total 89 units |
| Sai Signature | November 2023 | March 2028 | 90% | 1 unit booked out of 19 units for sale |
| Manshaya Apartments | November 2023 | December 2026 | 85% | 0 units booked out of total 27 units |
| Pardis Shingadia | February 2024 | April 2027 | 100% | 16 units booked out of 18 units for sale |
| Ambal Parijath Chsl | June 2023 | December 2026 | 90% | 5 units booked out of 9 units for sale |
About this project
Parsn Bhagyalakshmi by Parsn Lifespaces is a 32-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in October 2023 with possession due in May 2027. 17 units booked out of 19 units for sale. The concrete structure (RCC) is complete.
Read full summary
Parsn Bhagyalakshmi is a BMC-sanctioned project by Parsn Lifespaces in Chembur, Mumbai 400071, registered with MahaRERA as P51800053232. It was launched in October 2023. It has 32 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 32 units, 19 are for sale and 13 are the land-owner's share, not for sale.
Its registered possession date is May 2027, extended by 10 months from the original July 2026. Construction: excavation complete, structure (RCC) complete, final finishes not started.
17 units booked out of 19 units for sale (89%). Since the July 2026 update, 3 more units have been booked, the reported concrete structure (RCC) has gone from 88% to 100% and the possession date has moved from July 2026 to May 2027.