Mahindra Vista, Kandivali East
by Mahindra Lifespace Developers limited · Kandivali East, Mumbai 400101 · Map
- Launched
- Feb 2024First of 2 phases
- Possession (MahaRERA)
- Dec 2029 – Dec 2030Not extended
- Concrete structure
- 0%Weighted across 2 phases
- Booked
- 1,093 of 1,26786%
- Buildings
- 77.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 142
- 2 BHK
- 685
- 3 BHK
- 304
- 4 BHK
- 68
- Other units
- 68
- Total units
- 1,267
- Buildings
- 7
- Land
- 7.3 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Mahindra Vista Phase 1 Early stage | P51800054671 | 600 | 0% | 100% | |
| Mahindra Vista Phase 2 Early stage | P51800079147 | 599 | 0% | 74% |
Show updates by phase
Mahindra Vista Phase 1 (P51800054671)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 600 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Mahindra Vista Phase 2 (P51800079147)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 0% | 0% | 493 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Mahindra Vista by Mahindra Lifespace Developers limited (Mahindra Lifespaces) is a 1,267-unit BMC-sanctioned project in Kandivali East, Mumbai 400101, registered with MahaRERA in 2 phases, with possession dates from December 2029 to December 2030. 1,093 units booked out of total 1,267 units. Work on the concrete structure (RCC) has not started.
Read full summary
Mahindra Vista is a BMC-sanctioned project by Mahindra Lifespace Developers limited in Kandivali East, Mumbai 400101, registered with MahaRERA as 2 phases (P51800054671, P51800079147). The first phase was launched in February 2024. Together the phases have 1,267 units in 7 buildings: 1,199 homes (1, 2, 3 and 4 BHK) and 68 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from December 2029 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. Neither phase has its structure complete.
1,093 units booked out of total 1,267 units (86%).
Mahindra Lifespaces's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 4,150 |
| Completed without extending the possession date | 4 |
| Completed after an extension | 2 |
| Lapsed | 3 |
| Under construction | 8 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 5 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Mahindra Lifespaces projects | 4 (4 of 17 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.