Skip to main content

Mahindra Vista, Kandivali East

by Mahindra Lifespace Developers limited · Kandivali East, Mumbai 400101 · Map

Launched
Feb 2024First of 2 phases
Possession (MahaRERA)
Dec 2029 – Dec 2030Not extended
Concrete structure
0%Weighted across 2 phases
Booked
1,093 of 1,26786%
Buildings
77.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
142
2 BHK
685
3 BHK
304
4 BHK
68
Other units
68
Total units
1,267
Buildings
7
Land
7.3 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Mahindra Vista Phase 1
Early stage
P518000546716000%100%
Mahindra Vista Phase 2
Early stage
P518000791475990%74%
Show updates by phase

Mahindra Vista Phase 1 (P51800054671)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%600
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Mahindra Vista Phase 2 (P51800079147)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%493
0%0%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation75%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 75%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 75%Concrete structure (RCC) 0%Final finishes 0%

How to read construction stages

About this project

Mahindra Vista by Mahindra Lifespace Developers limited (Mahindra Lifespaces) is a 1,267-unit BMC-sanctioned project in Kandivali East, Mumbai 400101, registered with MahaRERA in 2 phases, with possession dates from December 2029 to December 2030. 1,093 units booked out of total 1,267 units. Work on the concrete structure (RCC) has not started.

Read full summary

Mahindra Vista is a BMC-sanctioned project by Mahindra Lifespace Developers limited in Kandivali East, Mumbai 400101, registered with MahaRERA as 2 phases (P51800054671, P51800079147). The first phase was launched in February 2024. Together the phases have 1,267 units in 7 buildings: 1,199 homes (1, 2, 3 and 4 BHK) and 68 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.

The phases' registered possession dates run from December 2029 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. Neither phase has its structure complete.

1,093 units booked out of total 1,267 units (86%).

Mahindra Lifespaces's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA17
Total units across these projects4,150
Completed without extending the possession date4
Completed after an extension2
Lapsed3
Under construction8
Possession date extended on the builder's application2
Typical time from launch to 100% structure5 years 4 months
MahaRERA complaints (filed by or against the builder), all Mahindra Lifespaces projects4 (4 of 17 projects)

See all Mahindra Lifespaces projects →