Mahindra Lifespaces projects in Mumbai

MahaRERA projects by Mahindra Lifespaces registered 2017–2026 in Mumbai.

Projects registered with MahaRERA17
Total units across these projects4,150
Full record

MahaRERA projects registered 2017–2026 in Mumbai

Completed without extending the possession date4
Completed after an extension2
Lapsed3
Under construction8
Possession date extended on the builder's application2
Typical time from launch to 100% structure5 years 4 months
MahaRERA complaints (filed by or against the builder), all Mahindra Lifespaces projects4 (4 of 17 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Andheri East (4) · Kandivali East (2) · Goregaon West (1) · Chandivali (1) · Mahalaxmi (1) · Ghatkopar East (1) · Malad West (1)

Under construction

ProjectVillageStagePossessionBooked
Mahindra BeaconHillMahalaxmiEarly stageDecember 203138 units booked out of total 199 units
Mahindra Marina64 · 3 phasesMalad WestEarly stageDec 2029 – Jun 2030196 units booked out of 299 units for sale
Mahindra Rainforest · 2 phasesGhatkopar EastEarly stageDec 2031306 units booked out of total 1,411 units
Mahindra Vista · 2 phasesKandivali EastEarly stageDec 2029 – Dec 20301,093 units booked out of total 1,267 units
Completed
ProjectVillageStatus
M SpaceGoregaon WestCompleted
RootsKandivali EastCompleted
Vicino A1A2Andheri EastCompleted
Vicino A3A4Andheri EastCompleted
Vicino A5A6Andheri EastCompleted
VivanteAndheri EastCompleted
Lapsed
ProjectVillageStatus
Mahindra AlcoveChandivaliLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us