Mahindra Lifespaces projects in Mumbai
MahaRERA projects by Mahindra Lifespaces registered 2017–2026 in Mumbai.
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 4,150 |
Full record
MahaRERA projects registered 2017–2026 in Mumbai
| Completed without extending the possession date | 4 |
|---|---|
| Completed after an extension | 2 |
| Lapsed | 3 |
| Under construction | 8 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 5 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Mahindra Lifespaces projects | 4 (4 of 17 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Andheri East (4) · Kandivali East (2) · Goregaon West (1) · Chandivali (1) · Mahalaxmi (1) · Ghatkopar East (1) · Malad West (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Mahindra BeaconHill | Mahalaxmi | Early stage | December 2031 | 38 units booked out of total 199 units |
| Mahindra Marina64 · 3 phases | Malad West | Early stage | Dec 2029 – Jun 2030 | 196 units booked out of 299 units for sale |
| Mahindra Rainforest · 2 phases | Ghatkopar East | Early stage | Dec 2031 | 306 units booked out of total 1,411 units |
| Mahindra Vista · 2 phases | Kandivali East | Early stage | Dec 2029 – Dec 2030 | 1,093 units booked out of total 1,267 units |
Completed
| Project | Village | Status |
|---|---|---|
| M Space | Goregaon West | Completed |
| Roots | Kandivali East | Completed |
| Vicino A1A2 | Andheri East | Completed |
| Vicino A3A4 | Andheri East | Completed |
| Vicino A5A6 | Andheri East | Completed |
| Vivante | Andheri East | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Mahindra Alcove | Chandivali | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.