Vallabh Krupa CHSL, Goregaon West
by Gun Rajan Constructions · Goregaon West, Mumbai 400104 · Map
- Launched
- Feb 20242 yrs 8 mths promised
- Possession (MahaRERA)
- Oct 2026Not extended
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 46 of 6472% · 43 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale46 booked out of 64 units
Rehab43 units for existing members
Total 107 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 42
- 2 BHK
- 32
- 3 BHK
- 18
- Other units
- 13
- Total units
- 107
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 64
- Rehab units
- 43
- Reserved units
- 25
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 0% | 46 | |
| 100% | 71% | 0% | 43 | |
| 100% | 50% | 0% | 22 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400104
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Oct 2026 | Dec 2026 |
| Concrete structure (RCC) | 80% | 89% |
| Units booked (free sale) | 72% | 57% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Vogue77, Goregaon West
- Building No.9 - Phase II, Goregaon West
- Redevelopment Of Mangal Karini CHSL, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vogue77 | May 2024 | December 2027 | 89% | 57 units booked out of total 79 units |
| Building No.9 - Phase II | June 2024 | December 2026 | 70% | 0 units booked out of total 52 units |
| Redevelopment Of Mangal Karini CHSL | August 2023 | December 2026 | 100% | 25 units booked out of 44 units for sale |
About this project
Vallabh Krupa CHSL by Gun Rajan Constructions is a 107-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in February 2024 with possession due in October 2026. 46 units booked out of 64 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Vallabh Krupa CHSL is a BMC-sanctioned project by Gun Rajan Constructions in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800054796. It was launched in February 2024. It has 107 units in 2 buildings: 94 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 107 units, 64 are for sale and 43 are rehab units for existing members.
Its registered possession date is October 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.
46 units booked out of 64 units for sale (72%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 71% to 80%.