Vogue77, Goregaon West
by Sahakar Builders & Developers · Goregaon West, Mumbai 400104 · Map
- Launched
- May 20243 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 89%Mid-construction
- Booked
- 57 of 7972% · 55 in Jul 2026
- Buildings
- 11 acre
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 10
- 3 BHK
- 19
- 4 BHK
- 44
- Other units
- 6
- Total units
- 79
- Buildings
- 1
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 89% | 10% | 57 | |
| 100% | 83% | 0% | 55 | |
| 90% | 53% | 0% | 47 | |
| 60% | 4% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400104
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 7 mths | 3 yrs 1 mth |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | May 2027 |
| Concrete structure (RCC) | 89% | 82% |
| Units booked | 72% | 78% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Building No.9 - Phase II, Goregaon West
- Redevelopment Of Om Manikanta Chsl, Goregaon West
- Ariha Vincere, Goregaon West
- Rivaan, Goregaon West
- Vallabh Krupa CHSL, Goregaon West
- Bali Serenity, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Building No.9 - Phase II | June 2024 | December 2026 | 70% | 0 units booked out of total 52 units |
| Redevelopment Of Om Manikanta Chsl | July 2024 | December 2027 | 70% | 29 units booked out of 43 units for sale |
| Ariha Vincere | July 2024 | June 2027 | 100% | 48 units booked out of 57 units for sale |
| Rivaan | July 2024 | December 2028 | 85% | 71 units booked out of 77 units for sale |
| Vallabh Krupa CHSL | February 2024 | October 2026 | 80% | 46 units booked out of 64 units for sale |
| Bali Serenity | December 2023 | March 2027 | 100% | 12 units booked out of 13 units for sale |
About this project
Vogue77 by Sahakar Builders & Developers is a 79-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in May 2024 with possession due in December 2027. 57 units booked out of total 79 units. The concrete structure (RCC) is 89% complete.
Read full summary
Vogue77 is a BMC-sanctioned project by Sahakar Builders & Developers in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800056048. It was launched in May 2024. It has 79 units in 1 building: 73 homes (2, 3 and 4 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 89% complete, final finishes 10% complete.
57 units booked out of total 79 units (72%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 83% to 89%.