Shree Kalptaru Chs Ltd, Ghatkopar East
by Conarch Lifespace LLP · Ghatkopar East, Mumbai 400075 · Map
- Launched
- Feb 20242 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 0 of 210% · 32 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 21 units
Rehab32 units for existing members
Total 53 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 21
- 3 BHK
- 11
- 4 BHK
- 2
- Other units
- 18
- Total units
- 53
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 21
- Rehab units
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 65% | 0% | 0% | 0 | |
| 65% | 0% | 0% | 0 | |
| 30% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400075
Projects with 10–70 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 2 yrs 5 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Jun 2026 |
| Concrete structure (RCC) | 0% | 94% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Shubham Athena, Ghatkopar East
- Shubham Aurum, Ghatkopar East
- Shubham Atlanta, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shubham Athena | January 2024 | June 2026 | 94% | – |
| Shubham Aurum | January 2024 | June 2026 | 94% | – |
| Shubham Atlanta | June 2023 | June 2026 | 100% | 39 units booked out of total 118 units |
About this project
Shree Kalptaru Chs Ltd by Conarch Lifespace LLP is a 53-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400075, launched in February 2024 with possession due in December 2026. 0 units booked out of 21 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Shree Kalptaru Chs Ltd is a BMC-sanctioned project by Conarch Lifespace LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800054893. It was launched in February 2024. It has 53 units in 2 buildings: 35 homes (1, 2, 3 and 4 BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 53 units, 21 are for sale and 32 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation 65% complete, structure (RCC) not started, final finishes not started.
0 units booked out of 21 units for sale (0%).