Shubham Atlanta, Ghatkopar East

Ready to moveLapsed

by Avvad Housing LLP · Ghatkopar East, Mumbai 400075 · Map

Launched
Jun 20233 yrs promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
39 of 11833%
Buildings
20.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
15
2 BHK
31
Other units
72
Total units
118
Buildings
2
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 20%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%39
100%100%90%–
100%100%90%–
100%100%20%39

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400075

Projects with 20–100 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400075
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 1 mth
Possession date extendedNo0 of 4
Possession date (MahaRERA)Jun 2026Nov 2026
Concrete structure (RCC)100%38%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Shubham Atlanta by Avvad Housing LLP is a 118-unit project in Ghatkopar East, Mumbai 400075, launched in June 2023; its MahaRERA registration has lapsed. 39 units booked out of total 118 units. The concrete structure (RCC) is complete.

Read full summary

Shubham Atlanta is a project by Avvad Housing LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800051726. It was launched in June 2023. It has 118 units in 2 buildings: 46 homes (1 and 2 BHK) and 72 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

39 units booked out of total 118 units (33%).