Skip to main content

Godrej Vistas, Vikhroli

by Godrej and Boyce Mfg. Co. Ltd · Vikhroli, Mumbai 400079 · Map

Launched
Mar 20245 yrs 9 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
100%Nearing possession
Booked
325 of 38285% · 277 in Jul 2026
Buildings
21.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
212
3 BHK
122
4 BHK
41
Other units
7
Total units
382
Buildings
2
Land
1.9 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%325
100%0%0%277
100%0%0%236
100%0%0%161

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Godrej Vistas by Godrej and Boyce Mfg. Co. Ltd is a 382-unit BMC-sanctioned project in Vikhroli, Mumbai 400079, launched in March 2024 with possession due in December 2029. 325 units booked out of total 382 units. The concrete structure (RCC) is complete.

Read full summary

Godrej Vistas is a BMC-sanctioned project by Godrej and Boyce Mfg. Co. Ltd in Vikhroli, Mumbai 400079, registered with MahaRERA as P51800055142. It was launched in March 2024. It has 382 units in 2 buildings: 375 homes (2, 3 and 4 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.

325 units booked out of total 382 units (85%). Since the July 2026 update, 48 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.

Godrej's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA35
Total units across these projects10,289
Completed without extending the possession date9
Completed after an extension0
Lapsed2
Under construction24
Possession date extended on the builder's application5
Typical time from launch to 100% structure6 years 3 months
MahaRERA complaints (filed by or against the builder), all Godrej projects86 (17 of 35 projects)

See all Godrej projects →