Godrej projects in Mumbai

MahaRERA projects by Godrej registered 2017–2026 in Mumbai.

Projects registered with MahaRERA35
Total units across these projects10,289
Full record

MahaRERA projects registered 2017–2026 in Mumbai

Completed without extending the possession date9
Completed after an extension0
Lapsed2
Under construction24
Possession date extended on the builder's application5
Typical time from launch to 100% structure6 years 3 months
MahaRERA complaints (filed by or against the builder), all Godrej projects86 (17 of 35 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Vikhroli (5) · Kandivali East (4) · Chembur (3) · Bandra West (3) · Bhandup West (2) · Worli (2) · Chandivali (1) · Mankhurd (1) · Mumbai Central (1) · Wadala West (1)

Under construction

ProjectVillageStagePossessionBooked
Godrej Avenue Eleven · 2 phasesMumbai CentralMid-constructionDec 2028 – Apr 2030359 units booked out of total 408 units
Godrej Bandra Bay Phase 1Bandra WestEarly stageNovember 20330 units booked out of total 182 units
Godrej Bandra Bay Phase 2Bandra WestEarly stageOctober 20350 units booked out of total 26 units
Godrej Bandra Bay Phase 3Bandra WestEarly stageOctober 20350 units booked out of total 24 units
Godrej BlissKandivali EastEarly stageNovember 2029231 units booked out of total 500 units
Godrej CarmichaelCumballa HillMid-constructionDecember 20309 units booked out of 11 units for sale
Godrej Five GardensMatungaMid-constructionDecember 202845 units booked out of total 76 units
Godrej Horizon · 3 phasesWadala WestMid-constructionMay 2028 – Jun 2031878 units booked out of total 1,114 units
Godrej Nurture · 2 phasesBhandup WestEarly stageMar 2032 – Jul 2032310 units booked out of total 616 units
Godrej Reserve · 5 phasesKandivali EastMid-constructionJun 2030 – Jun 20311,604 units booked out of total 1,683 units
Godrej Sky TerracesMankhurdNearing possessionMarch 202970 units booked out of total 76 units
Godrej SkyshoreVersovaEarly stageDecember 203192 units booked out of total 138 units
Godrej SquareBhandup WestEarly stageOctober 202879 units booked out of total 89 units
Godrej Trilogy SeafrontWorliEarly stageDecember 2034128 units booked out of total 166 units
Godrej Trilogy SeaturfWorliEarly stageDecember 2033101 units booked out of total 122 units
Godrej VistasVikhroliNearing possessionDecember 2029325 units booked out of total 382 units
Completed
ProjectVillageStatus
Godrej CentralChemburCompleted
Godrej PlatinumVikhroliCompleted
Godrej RKSChemburCompleted
Godrej TranquilKandivali EastCompleted
Godrej TwoVikhroliCompleted
Godrej Urban ParkChandivaliCompleted
The Trees ResidentialVikhroliCompleted
The Trees, OriginsVikhroliCompleted
Lapsed
ProjectVillageStatus
Godrej NestKandivali EastLapsed
Godrej PrimeChemburLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.